On-site duration
3 weeks
Modern Shaker Kitchen — completed view

A 1930s semi where the kitchen had been broadly the same since the 1990s. Three weeks on site, replaced with a quiet greige shaker run, a quartz waterfall island and a marble splashback that lifts the whole room.

Scope of work

  • Full strip-out of the existing kitchen including units, worktops, splashback tiles and old vinyl flooring.
  • Plaster repairs and a skim coat where the original tiling had been hacked off.
  • Electrical first-fix for the new appliance positions plus relocated socket runs above the worktop.
  • Gas-Safe re-certification of the hob connection after the unit was repositioned.
  • Bespoke shaker carcasses fitted with chrome bar pulls, including a tall pantry tower flanking the range.
  • Full-slab quartz worktop templated after the carcasses were in and fitted a week later.
  • Marble splashback behind the range, mitred to wrap the corner cleanly.

Challenges we solved

  • The original walls were noticeably out of square — every plinth, worktop end and pantry filler was cut bespoke on site rather than supplied to a standard length.
  • The existing hob feed sat in a position that wouldn't suit the new layout — re-routed and re-certified by a Gas Safe engineer rather than left in place.
  • Quartz could only be templated after the carcasses were physically installed, which forced a one-week gap mid-programme. We used the gap to fit the splashback and decorate the room, so the kitchen wasn't sat idle.

Process & execution

  1. Days 1–3 · Strip-out + plaster

    Old kitchen removed in a single day; plaster repairs where the existing tiling came off; floor protection laid for the rest of the programme.

  2. Days 4–6 · First fix

    Electrical first-fix for new socket positions, plumbing for the new sink position, gas re-routing and Gas Safe re-cert booked.

  3. Days 7–10 · Units in

    Bespoke shaker carcasses delivered and fitted in sequence — base units first, then tall units flanking the range, doors and drawers hung last.

  4. Days 11–14 · Quartz template + splashback

    Quartz templated end of week two; splashback fitted while the slab was being machined; room redecorated.

  5. Days 15–18 · Quartz fit + appliances + handover

    Worktop fitted, sink and hob commissioned, appliances integrated and tested, full clean, walkthrough.

Materials & finishes

  • Bespoke shaker doors in matte greige with chrome bar pulls
  • Full-slab quartz worktop, island waterfall ends
  • Veined marble splashback behind the range, mitred returns
  • Stainless steel French-door fridge
  • Brushed-brass mixer tap with separate filtered-water spout
  • Integrated dishwasher and double oven

Outcome

A bright, hard-working family kitchen that finally fits the shape of the room. The original layout is broadly retained, but every cabinet end and worktop edge has been cut to fit — so nothing reads as off-the-shelf despite using a standard trade-brand carcass system.